Member News: Spittal-Peterhead subsea cable link reaches milestone as construction compounds become operational

October 6, 2026
Member News: Spittal-Peterhead subsea cable link reaches milestone as construction compounds become operational

SSEN Transmission has reached a major milestone in the delivery of its Spittal to Peterhead subsea cable link project, with the main construction compounds at both the northern and southern ends of the route now fully established and operational.

Located at Bower Quarry near Halkirk in Caithness and Blackhills near Peterhead, the sites will serve as the primary bases for the onshore cable installation works, supporting construction activity along the route in the months ahead. The facilities include office accommodation, welfare facilities and storage areas for project teams and supply chain partners involved in delivering the onshore cable package. Around 50 staff are currently based at the Bower Quarry facility, representing organisations including SSEN Transmission, principal contractor NKT and Caithness-based contractor John Gunn and Sons.

In the south, 23 permanent staff from SSEN Transmission, NKT and Aberdeenshire-based contractor Nicol of Skene are now based at the Blackhills site. Local workers will continue to be employed across both sites as the project progresses, while the opportunities created by the project are helping local contractors grow their workforces.

The establishment of both construction compounds marks an important step forward for the project, which will create a 166km, 2GW High Voltage Direct Current (HVDC) subsea cable link between Sinclair’s Bay in Caithness and Rattray Head near Peterhead. The link will connect into the new Banniskirk Hub in Caithness and Netherton Hub near Peterhead in Aberdeenshire.

 

The milestone comes as Horizontal Directional Drilling (HDD) activities continue at Rattray Head, where a 1.7km drill is being constructed creating one of the UK’s longest power cable landfall connections. The technique enables the cable to be installed in pipes beneath the coastline minimising impacts on the local environment and surrounding area. Work at Rattray Head is expected to progress over the next 12 months, while similar HDD activities at Sinclair’s Bay are scheduled to begin in late 2027.

Niall Macleod, Project Director for SSEN Transmission’s Spittal to Peterhead HVDC subsea link, said:

“The establishment of our main compounds in both Caithness and Aberdeenshire represents an important milestone for the Spittal to Peterhead project.

“These facilities will act as the operational centres for our teams and supply chain partners, including local businesses John Gunn and Sons and Nicol of Skene, as we progress construction of this critical infrastructure project. With both sites now in place, we’re well positioned to move forward with the next stages of delivery.”

 

Get in touch

AREG is the original energy transition organisation, working on behalf of members to empower the energy supply chain and champion its expertise. Please get in touch if you have any questions or would like to find out more about membership.

“

AREG has played an important role in the growth of Scotland’s renewable energy sector, engaging the supply chain and developing the European Offshore Wind Deployment Centre. However, we are only at the very beginning of the transition that AREG was established to both lead and support so there are still opportunities for companies to get into the constantly evolving renewables supply chain. We look forward to continuing our work together as renewables builds on its place as Scotland’s main source of power, and as we seek to deliver real change in the crucial areas of heat and transport.

Scottish Renewables
“

Aberdeen & Grampian Chamber of Commerce has worked closely with AREG since its formation. The recent progress in the developments of offshore wind projects by Equinor and Vattenfall are as a result of the work of the group over many years. The north-east is known as the oil and gas capital of Europe. At the Chamber, we believe the region must evolve its position to being recognised as the energy capital. Whilst hydrocarbons will continue to be essential in driving our economy for years to come, the generation of renewable resources will play an increasingly important role in providing cost-effective power, innovative development and economic growth.

Aberdeen & Grampian Chamber of Commerce
“

The enthusiasm and dedication of the early group that would become AREG was fundamental in us choosing to launch All-Energy in Aberdeen. The first tiny show was held in 2001, and AREG’s Chairman at the time, Jeremy Cresswell, played such an active role that I often describe him in terms such as All-Energy’s ‘midwife’. All-Energy is now the UK’s largest renewable and low carbon energy exhibition and conference in terms of number of attendees, space booked, and number of exhibiting companies. As AREG became firmly established, their presence and support for the event grew spectacularly over the years. We thank them most sincerely for their invaluable input.

All-Energy
“

Vattenfall has forged a strong working relationship with AREG through the development of the European Offshore Wind Deployment Centre. AREG has worked tirelessly on behalf of the North East and it can take enormous credit for the growth of sustainable energy in the region and the path it has cleared for the region to capture further investment.

Vattenfall
“

Aberdeen City and Shire is emerging as a key location for renewables by successfully transferring its world-class oil and gas expertise into the sector and AREG has done much to advance this through a broad range of initiatives. It has acted as a catalyst in driving further investment in the local economy by engaging with companies, Government, public bodies and existing projects and we have been pleased to support their efforts. Scottish Enterprise will continue to engage with AREG as we increase Scotland’s use of renewable energy.

Scottish Enterprise