Member News: SSEN Transmission outlines plans to strengthen and secure east coast electricity network

May 19, 2026
Member News: SSEN Transmission outlines plans to strengthen and secure east coast electricity network
  • New and replacement substation projects will secure local supply while enabling growth in clean energy generation
  • Proposals include the removal of around 82km overhead line between southern Aberdeenshire and Angus, reducing cumulative impact of proposed infrastructure
  • Plans also in development for new north-east overhead line reinforcement and substation project, with consultation dates to be announced later this month

SSEN Transmission has set out plans to upgrade the electricity transmission network between southern Aberdeenshire and Angus, ensuring a secure supply of electricity for local communities while enabling future clean power connections and reducing the cumulative impact of overhead lines along Scotland’s east coast.

The proposals, which are outlined in a booklet that is now available to the public, include the replacement of two substations, and the construction of a new one.

The plans also include the removal of around 82km of 132kV overhead line between Craigiebuckler in Aberdeen and Monikie in southern Angus. The line, which is around 70 years old, is nearing the end of its operational capabilities.

Removing this ageing infrastructure, which consists of over 550 steel towers and wooden poles, is essential to maintain network reliability. It will also help to reduce the cumulative impact of current and proposed overhead line projects between Aberdeenshire and Angus.

To enable its dismantling, two substations at Fiddes and Bridge of Dun that provide power to Stonehaven, Montrose, Brechin and surrounding communities would be replaced and reconnected to the existing transmission network at different locations, via new 132kV overhead line or underground cable connections.

These replacement substations would be located within the vicinity of the existing sites, be of a similar size, and would ultimately allow the existing sites to be demolished as part of the overhead line removal programme.

At Fiddes, this would see a new connection to the upgraded Fetteresso 132kV substation near Stonehaven, where plans will be submitted to upgrade the substation to support both local demand and future growth, including plans to electrify the East Coast railway.

Meanwhile, a 275kV substation is proposed in the area around Brechin and Edzell.

Known as the East Coast substation, this would connect into the existing Kintore to Tealing 275kV overhead line through new tie-ins, while a new Bridge of Dun substation would also be established and connected to the 275kV substation via 132kV overhead line or underground cable circuits.

Consultation is planned later this year for the Fiddes and Bridge of Dun substation projects.  A series of consultation events will take place  in May for the East Coast substation, as follows:

  • Monday 25 May 2026, 2-7pm Inglis Memorial Hall, Edzell, Brechin
  • Tuesday 26 May 2026, 2-7pm Stracathro Parish Hall, Inchbare, Brechin
  • Wednesday 27 May 2026, 1-6pm Craigo Community Hall, Craigo
  • Thursday 28 May 2026, 2-7pm Brechin City Hall, 9 Swan Street, Brechin,

Alison Hall, Director of Development for SSEN Transmission, said:

“We’re pleased to share early proposals for changes to transmission infrastructure on Scotland’s east coast, including the removal of around 82km of existing infrastructure. These form part of key network upgrades that will play a vital role in enabling new clean energy generation, increasing energy security, and delivering substantial economic and legacy benefits.

“Together, these proposals would support a secure electricity supply for local communities while reducing the cumulative impact of transmission infrastructure through the dismantling of existing overhead lines.

“At this early stage, no final decisions have been made on sites or technology, and public feedback will play an important role as we develop our plans.

“Our upcoming consultation events on a proposed new East Coast 275kV substation are the first opportunity for communities to share their views, and I would encourage anyone with an interest to attend and provide feedback.”

In addition to these proposals, SSEN Transmission is also intending to hold consultation events in early June for a separate project to upgrade the existing Peterhead to Kintore 275kV overhead line in north-east Scotland to 400kV operation. Like the proposed projects between Aberdeenshire and Angus, this forms part of SSEN Transmission’s investment of around £29bn to upgrade the electricity transmission network across the north of Scotland in the coming years.

Further information on these plans, including proposals for a new substation in the south Formartine area, will be made available later this month along with consultation dates. The exact location of the proposed substation is yet to be selected.

Get in touch

AREG is the original energy transition organisation, working on behalf of members to empower the energy supply chain and champion its expertise. Please get in touch if you have any questions or would like to find out more about membership.

AREG has played an important role in the growth of Scotland’s renewable energy sector, engaging the supply chain and developing the European Offshore Wind Deployment Centre. However, we are only at the very beginning of the transition that AREG was established to both lead and support so there are still opportunities for companies to get into the constantly evolving renewables supply chain. We look forward to continuing our work together as renewables builds on its place as Scotland’s main source of power, and as we seek to deliver real change in the crucial areas of heat and transport.

Scottish Renewables

Aberdeen & Grampian Chamber of Commerce has worked closely with AREG since its formation. The recent progress in the developments of offshore wind projects by Equinor and Vattenfall are as a result of the work of the group over many years. The north-east is known as the oil and gas capital of Europe. At the Chamber, we believe the region must evolve its position to being recognised as the energy capital. Whilst hydrocarbons will continue to be essential in driving our economy for years to come, the generation of renewable resources will play an increasingly important role in providing cost-effective power, innovative development and economic growth.

Aberdeen & Grampian Chamber of Commerce

The enthusiasm and dedication of the early group that would become AREG was fundamental in us choosing to launch All-Energy in Aberdeen. The first tiny show was held in 2001, and AREG’s Chairman at the time, Jeremy Cresswell, played such an active role that I often describe him in terms such as All-Energy’s ‘midwife’. All-Energy is now the UK’s largest renewable and low carbon energy exhibition and conference in terms of number of attendees, space booked, and number of exhibiting companies. As AREG became firmly established, their presence and support for the event grew spectacularly over the years. We thank them most sincerely for their invaluable input.

All-Energy

Vattenfall has forged a strong working relationship with AREG through the development of the European Offshore Wind Deployment Centre. AREG has worked tirelessly on behalf of the North East and it can take enormous credit for the growth of sustainable energy in the region and the path it has cleared for the region to capture further investment.

Vattenfall

Aberdeen City and Shire is emerging as a key location for renewables by successfully transferring its world-class oil and gas expertise into the sector and AREG has done much to advance this through a broad range of initiatives. It has acted as a catalyst in driving further investment in the local economy by engaging with companies, Government, public bodies and existing projects and we have been pleased to support their efforts. Scottish Enterprise will continue to engage with AREG as we increase Scotland’s use of renewable energy.

Scottish Enterprise